Japan: Nitrogen injected to avert another nuclear plant explosion

0 CommentsPrint E-mail China.org.cn, April 7, 2011
Adjust font size:

Tokyo Electric Power Company says it has started injecting nitrogen gas into the containment vessel of a reactor at the crippled Fukushima Daiichi nuclear power plant to prevent hydrogen gas from exploding inside the vessel.

The nuclear fuel rods in the Unit 1 reactor are still nearly half exposed as the coolant water inside the reactor has not covered them, despite weeks of pumping first sea water and then fresh water into the reactor.

The cooling systems for the plant's six reactors and spent fuel pools were lost when outside power and emergency power failed after the deadly March 11 earthquake and tsunami.

The company fears that hydrogen and oxygen are being released by the reaction between the cooling water and the zirconium alloy that covers the fuel. Hydrogen also can be released when water molecules are broken apart by radiation.

Injection of nitrogen is intended to displace oxygen inside the containment vessel, thereby reducing a risk of explosion due to the combustible combination of hydrogen and oxygen, according to the International Atomic Energy Agency. Chemically stable nitrogen gas does not react with hydrogen.

Increasing hydrogen density inside the containment vessel heightens the risk of an explosion like those that blasted through Unit 1 on March 12, Unit 3 on March 14, and Unit 4 on March 15.

The nitrogen injections have been approved by the Ministry of Economy, Trade and Industry and are expected to continue for six days.

Work to inject nitrogen gas into the Unit 1 reactor containment vessel began at 10:30 pm Wednesday, and the actual injection began at 1:30 am Thursday, local time.

The company is also considering making similar injections in the Unit 2 and 3 reactors.

The Nuclear and Industrial Safety Agency warns that the nitrogen gas injection could cause gases, including radioactive substances, to leak outside the reactor containment vessel. The agency has directed TEPCO to monitor radioactivity in surrounding areas and to fully disclose its findings.

TEPCO has had success in stopping the leak of highly radioactive water into the Pacific Ocean from the damaged power plant.

On Saturday, the company found that a concrete pit where supply cables are stored outside the Unit 2 reactor was leaking from a crack in the concrete.

On Tuesday, the plant operator drilled a hole into a layer of gravel around the pit, and poured a hardening agent called liquid glass, or sodium silicate, to stop the leak.

On Wednesday morning, TEPCO said the flow was confirmed to have stopped.

"Today at 5:38 am, we have observed stoppage of spilling of water from the crack on the concrete lateral of the pit," TEPCO said in a statement. "For the sake of completeness, we put further reinforcement for the stoppage of leakage and consider countermeasure including continuous injection of coagulant."

The company said the water level in the Unit 2 turbine building and in the pit remains unchanged, indicating no further leakage. Workers are checking for other cracks that could leak radioactive water.

In sampling of seawater in front of a screen near the pit, TEPCO has found three nuclides - iodine 131, cesium 134 and cesium 137 - and is now testing for other radionucleides in accordance with directions from the Nuclear and Industrial Safety Agency.

At the same time, TEPCO is deliberately releasing about 8,000 tons of wastewater contaminated with low-level radiation into the ocean to make room in storage tanks for highly radioactive water. The company says about 6,000 tons of water have been released to date, with government approval and over the objections of the National Federation of Fisheries Cooperative Associations.

The company is spraying a synthetic resin solution on the plant's premises to prevent radioactive dust from becoming airborne. On Wednesday, the resin was sprayed over a 300 square meter (3,230 square foot) area around a spent nuclear fuel pool.

Radioactive debris and dust were spread across the facility by the hydrogen explosions at the Unit 1, 2, and 3 reactors in March.

Print E-mail Bookmark and Share

Go to Forum >>0 Comments

No comments.

Add your comments...

  • User Name Required
  • Your Comment
  • Racist, abusive and off-topic comments may be removed by the moderator.
Send your storiesGet more from China.org.cnMobileRSSNewsletter
主站蜘蛛池模板: 妞干网在线免费视频| 黑人巨茎大战俄罗斯美女| 成人免费无码精品国产电影| 久久综合香蕉久久久久久久| 欧美日韩国产色综合一二三四| 免费A级毛片无码免费视频首页| 手机看片福利日韩国产| 成人综合国产乱在线| 亚洲成人免费电影| 琪琪see色原网一区二区| 又大又黄又粗又爽视频| 777奇米影视视频在线播放| 成人欧美精品大91在线| 久久国产亚洲高清观看| 欧美老熟妇欲乱高清视频| 免费在线看视频| 精品视频一区二区三三区四区| 国产乱码一区二区三区爽爽爽| 国产对白精品刺激一区二区| 国产精品亚洲一区二区三区| 91福利电影福利在线观看| 把极品白丝班长啪到腿软| 亚洲天堂中文字幕| 波多野结衣制服诱惑| 国产一级小视频| 麻豆国产三级在线观看| 国产欧美日韩精品a在线观看| 尤物yw午夜国产精品视频| 国产精品美女久久久久| 91精品国产综合久久青草| 在线播放国产不卡免费视频| av无码一区二区三区| 日本三人交xxx69视频| 久久精品99无色码中文字幕| 最近日本字幕免费高清| 亚洲色图15p| 老子影院午夜伦手机不四虎| 国产二级一片内射视频播放| 阿娇囗交全套高清视频| 国产精品午夜剧场| mm1313亚洲精品无码又大又粗|