Windbreak wall built along south Xinjiang railway
Adjust font size:

On October 18, 2007, the final section of a railway windbreak wall was completed in south Xinjiang Uygur Autonomous Region. Finished two days ahead of schedule, the wall is expected to provide an effective shield against wind for trains that run between Zhenzhuquan and Hongshanqu. The China Railway 15th Construction Bureau is in charge of the project. Tianshan.net.cn reported from Xinjiang.

The newly built windbreak wall extends a total length of 8,230 meters.? A forty-meter section was built with state-of-the-art technology that had never been used in China before. This section of the windbreak wall is expected to provide safety shelter for both the railway and the highway.

The windbreak wall was constructed under extremely difficult conditions. After the project began on August 20, the work team encountered winds on 18 days out of the total 58. Over half of the work period the surface temperature on the construction site remained above 40 degrees centigrade.

Because of the busy traffic between Zhenzhuquan and Hongshanqu, train service was not halted during construction. The construction team worked out a series of precautionary measures to ensure the workers' safety. Furthermore, when construction took place along the highway, the project team managers kept in close contact with local traffic authorities in charge of the temporary traffic control near the construction site. Previously, optical cables had been laid underground along the railway. To build this windbreak wall, the project team worked together with relevant departments and relocated the cables off site.

The windbreak wall is of great significance toward the safe operation of the railway in south Xinjiang. The project team accepted a tight timetable in order to complete the wall as early as possible. Headed by energetic and experienced engineers, they worked day and night and managed to build up the high quality wall two days ahead of schedule.

Trains running between Zhenzhuquan and Hongshanqu are constantly struck by hurricane-force winds combined with sand and stones. After the entire windbreak wall has been constructed passengers will enjoy a safer and more comfortable trip in south Xinjiang Uygur Autonomous Region.

(China.org.cn by Chen Xia, October 25, 2007)

Tools: Save | Print | E-mail | Most Read
Comment
Pet Name
Anonymous
China Archives
Related >>
Most Viewed >>
主站蜘蛛池模板: 久久青青草原亚洲av无码麻豆| 免费a级毛片高清在钱| 青青草原免费在线| 天天躁夜夜踩狠狠踩2022| 中文字幕丰满乱孑伦无码专区| 日韩AV无码一区二区三区不卡 | 国产大学生粉嫩无套流白浆| 影音先锋男人看片资源| 在线播放真实国产乱子伦| 伊人热热久久原色播放www| 男人天堂免费视频| 在线一区二区观看| javaparser日本高清| 日韩欧群交p片内射中文| 亚洲午夜一区二区电影院| 欧美精品v国产精品v日韩精品 | 最近完整中文字幕2019电影| 亚洲国产欧美视频| 欧美疯狂性受xxxxx喷水| 亚洲熟女综合色一区二区三区| 爱做久久久久久| 低头看我是怎么c哭你的细节| 精品亚洲成AV人在线观看| 和桃子视频入口网址在线观看| 菠萝蜜视频在线观看免费视频| 国产免费一期二期三期四期| 黄色网在线播放| 国产成人亚洲精品无码av大片 | 国产日韩在线看| 五月婷婷一区二区| 国产精品一区欧美激情| 在线www中文在线| 国产精品国产亚洲精品看不卡| 77777_亚洲午夜久久多人| 国产超爽人人爽人人做| 91探花视频在线观看| 国产资源在线看| 37大但人文艺术a级| 国产精品成人网| а√天堂地址在线| 小sao货水好多真紧h视频|