Qinghai-Tibet Railway Chugging Along
Adjust font size:

A diesel locomotive, the last of 30 needed in the Qinghai-Tibet Railway Project arrived at the Amdo track-laying base in Tibet on June 14, all 138 tons of it. The locomotive was dismantled into three parts and was carried in three trucks from the Xiushui River base to Amdo, a distance of some 400 kilometers.

 

 

The journey from Xiushui River to Amdo is fraught with difficulties mainly due to terrain and climate. For one thing, average elevation is 4,800 meters. For another, the weather isn't always kind, particularly the traverse over Tanggula and Fenghuo mountains, both at an elevation of over 5,000 meters. Further, passing through the source of the Yangtze River, Tuotuo River, is a challenge in itself.

 

The railway is expected to be operational from July 1, 2007. But its construction is a mammoth project, which is why the Ministry of Railways decided last year to add the Amdo track-laying base to the construction plan.

 

The move has conspicuously speeded up the general construction process, not least because the tracks are being laid in both directions?-- towards Tanggula and towards Lhasa.

 

Tracks are now being laid on the Tanggula Mountain ridge, and the long continuous downhill at Damxung-Lhasa.

 

 

As with transporting the locomotive, the track-laying is not without its challenges. For example, 50 kilometers to the left and right of the Tanggula Mountain ridge, the railway’s highest point, workers have to cope with hailstorms, heavy rain, snow and wind. Temperatures can dip to as low as 20o C below zero. Bad weather conditions pose a great threat to the workers' safety. Reduced oxygen levels at such high altitudes also lowers work efficiency and affects machine performance, said La Youyu, vice head of the general command of the railway construction.

 

To tackle these issues, construction headquarters has drawn up a plan to ensure that the track-laying goes smoothly. For the long continuous downhill portion of the project, tracks are laid at 3.2 kilometers per day on average and 3 kilometers per day in the tunnels. In addition, working hours have been shortened to prevent fatigue, and safety examination and maintenance procedures in relation to equipment have been enhanced.

 

The Qinghai-Tibet Railway will run from the city of Golmud in western Qinghai to Lhasa, the capital of the Tibet Autonomous Region, extending across a total length of 1,142 kilometers.

 

(China.org.cn by Zhang Tingting, June 24, 2005)

Tools: Save | Print | E-mail | Most Read
Comment
Pet Name
Anonymous
China Archives
Related >>
- Rail Improves Ecosystem
- World's 'Highest' Railway Environment-friendly: SEPA
- Over a Half of Tracks Laid for Qinghai-Tibet Railway
- Vice-Premier Calls for Sound Construction of Qinghai-Tibet Railway
- Qinghai-Tibet Railway to Start Trial Operation in 15 Months
- Warm Weather May Threaten World's Highest Railway
Most Viewed >>
- World's longest sea-spanning bridge to open
- Yao out for season with stress fracture in left foot
- 141 seriously polluting products blacklisted
- China starts excavation for world's first 3G nuclear plant
- Irresponsible remarks on Hu Jia case opposed 
- 'The China Riddle'
- China, US agree to step up constructive,cooperative relations
- FIT World Congress: translators on track
- Christianity popular in Tang Dynasty
- Factory fire kills 15, injures 3 in Shenzhen

Product Directory
China Search
Country Search
Hot Buys
主站蜘蛛池模板: 六月婷婷综合网| 国产日韩精品一区二区在线观看 | 久久综合伊人77777| 欧美激情xxxx性bbbb| 众多明星短篇乱淫小说| 美女张开腿让男人桶| 国产乱码精品一区三上| 丁香婷婷六月天| 国产精品亚洲va在线观看| 91大神精品网站在线观看| 天天看天天摸色天天综合网 | 午夜无码国产理论在线| 色综合综合色综合色综合| 国产尤物二区三区在线观看| 天天影院成人免费观看| 国产精品无码久久久久| 91精品国产免费网站| 在线观看黄网址| 人人妻人人澡人人爽曰本| 精品视频vs精品视频| 国产一区二区三区久久| 贵州美女一级纯黄大片| 国产区在线视频| 黄软件在线观看| 大香伊蕉国产av| www.日韩在线| 嫩草影院在线免费观看| 一级黄色免费网站| 成人免费777777| 中国明星16xxxxhd| 成年人一级毛片| 中文在线三级中文字幕| 新婚夜被别人开了苞诗岚| 亚洲av色无码乱码在线观看| 欧美激情二区三区| 亚洲欧洲另类春色校园网站| 欧美黑人又粗又硬xxxxx喷水| 亚洲精品成人网站在线播放| 热re久久精品国产99热| 亚洲综合色视频在线观看| 熟女性饥渴一区二区三区|