Qinghai-Tibet Railway Chugging Along
Adjust font size:

A diesel locomotive, the last of 30 needed in the Qinghai-Tibet Railway Project arrived at the Amdo track-laying base in Tibet on June 14, all 138 tons of it. The locomotive was dismantled into three parts and was carried in three trucks from the Xiushui River base to Amdo, a distance of some 400 kilometers.

 

 

The journey from Xiushui River to Amdo is fraught with difficulties mainly due to terrain and climate. For one thing, average elevation is 4,800 meters. For another, the weather isn't always kind, particularly the traverse over Tanggula and Fenghuo mountains, both at an elevation of over 5,000 meters. Further, passing through the source of the Yangtze River, Tuotuo River, is a challenge in itself.

 

The railway is expected to be operational from July 1, 2007. But its construction is a mammoth project, which is why the Ministry of Railways decided last year to add the Amdo track-laying base to the construction plan.

 

The move has conspicuously speeded up the general construction process, not least because the tracks are being laid in both directions?-- towards Tanggula and towards Lhasa.

 

Tracks are now being laid on the Tanggula Mountain ridge, and the long continuous downhill at Damxung-Lhasa.

 

 

As with transporting the locomotive, the track-laying is not without its challenges. For example, 50 kilometers to the left and right of the Tanggula Mountain ridge, the railway’s highest point, workers have to cope with hailstorms, heavy rain, snow and wind. Temperatures can dip to as low as 20o C below zero. Bad weather conditions pose a great threat to the workers' safety. Reduced oxygen levels at such high altitudes also lowers work efficiency and affects machine performance, said La Youyu, vice head of the general command of the railway construction.

 

To tackle these issues, construction headquarters has drawn up a plan to ensure that the track-laying goes smoothly. For the long continuous downhill portion of the project, tracks are laid at 3.2 kilometers per day on average and 3 kilometers per day in the tunnels. In addition, working hours have been shortened to prevent fatigue, and safety examination and maintenance procedures in relation to equipment have been enhanced.

 

The Qinghai-Tibet Railway will run from the city of Golmud in western Qinghai to Lhasa, the capital of the Tibet Autonomous Region, extending across a total length of 1,142 kilometers.

 

(China.org.cn by Zhang Tingting, June 24, 2005)

Tools: Save | Print | E-mail | Most Read
Comment
Pet Name
Anonymous
China Archives
Related >>
- Rail Improves Ecosystem
- World's 'Highest' Railway Environment-friendly: SEPA
- Over a Half of Tracks Laid for Qinghai-Tibet Railway
- Vice-Premier Calls for Sound Construction of Qinghai-Tibet Railway
- Qinghai-Tibet Railway to Start Trial Operation in 15 Months
- Warm Weather May Threaten World's Highest Railway
Most Viewed >>
- World's longest sea-spanning bridge to open
- Yao out for season with stress fracture in left foot
- 141 seriously polluting products blacklisted
- China starts excavation for world's first 3G nuclear plant
- Irresponsible remarks on Hu Jia case opposed 
- 'The China Riddle'
- China, US agree to step up constructive,cooperative relations
- FIT World Congress: translators on track
- Christianity popular in Tang Dynasty
- Factory fire kills 15, injures 3 in Shenzhen

Product Directory
China Search
Country Search
Hot Buys
主站蜘蛛池模板: 很污很黄的网站| 欧美69式视频在线播放试看| 四虎成人精品国产永久免费无码| 免费看的黄网站| 国产色秀视频在线观看| h国产在线观看| 成人au免费视频影院| 久久久久国产午夜| 日韩精品视频免费网址| 亚洲区小说区激情区图片区| 污到下面流水的视频| 你懂的免费视频| 精品无码国产污污污免费网站| 日本插曲的痛的30分钟| 亚洲av本道一区二区三区四区| 欧美视频在线观看免费最新| 日批免费观看视频| 久久精品一区二区三区中文字幕| www.成年人视频| 日本一区二区三| 久久综合给合久久狠狠狠97色| 欧美性xxxx偷拍| 亚洲欧美电影一区二区| 特级做a爰片毛片免费看一区| 免费看国产曰批40分钟| 美女毛片一区二区三区四区| 国产乱人伦偷精品视频| 领导边摸边吃奶边做爽在线观看 | 一级做a爰片性色毛片中国| 无翼乌日本漫画| 久久久久久国产精品视频| 日本成日本片人免费| 久久国产精品老人性| 日韩内射美女片在线观看网站 | 欧美一级在线视频| 亚洲成a人一区二区三区| 欧美最猛黑人xxxx黑人| 亚洲欧美日韩高清在线看| 毛片a级三毛片免费播放| 亚洲精品中文字幕乱码| 永久免费a∨片在线观看|