Olympic Village profile
Adjust font size:

Profile

The Olympic Village lies in the northwest corner of the Beijing Olympic Green, with the Olympic competition venues to its south and the Forest Park to its north.

The Village, with an area of 66 hectares, includes the Apartment Buildings for athletes in the south and the overlay area in the north.

During the Olympic Games, the Olympic Village can accommodate more than 16,000 athletes and officials (7,000 athletes and officials during the Paralympic Games) and provide services related to accommodation, living, training, leisure, entertainment, etc.

The Residential Zone

The Residential Zone has an area of 27.55 hectares and a floor area of 524,000 square meters. They include 20 9-storey buildings, 22 6-storey buildings, 3 Super Resident Centres, 9 Resident Centres and facilities, such as the Polyclinic and the Casual Dining Hall. Overlay area in the north

The overlay area in the north of the village will provide services including arrival, accreditation, leisure, catering, fitness, departure, etc. for athletes coming to the Olympic and Paralympic Games.

There will be the Welcome Ceremony Stage, the Village Mayor Office, the Dining Hall, the shopping centre, the logistics centre, the accreditation centre, etc.

Construction

The Structural Engineering: outer facade is fitted up and the indoor fine decoration has been completely largely.

Water supply and drainage system: the pipes to supply water for daily life, potable water, reclaimed water for flushing toilets, hot water for shower, and water for fire fighting have been installed. Sewers have been installed.

The electrical equipment: outdoor power system, switching station, electricity distribution room, room lighting and indoor panel box systems have been installed. And the full loading operation has been carried out. The elevator has been installed. The construction of the intelligent systems (building automation, fire control, office, security, communication, automatic control) has entered the final stage.

Air conditioning and heating: the first phase commissioning of air conditioning was completed in September 2007. The heating for winter is underway.

Landscape project: the engineering for road surface course, outdoor lighting, green space and water system, enclosure and gate is close to the end. Main building and outdoor engineering have been completed largely The public space, such as staircases and elevator halls, has been fitted up The indoor fine decoration has been completed largely Water supply and drainage system and sanitary wares have been installed. The elevations have been installed

Air conditioning system with water reclamation heat pumps has been put into operation.

Follow-up

Before Lockdown (begins on July 8th, 2008): The full loading test is scheduled to be carried out according to the actual need during the Games-time. During the test, the shower water, potable water, tap water, drainage, outdoor and indoor lighting, elevator, intelligentization and other systems will be tested; the water reclamation heat pump system will be put into operation for cooling purpose with automatic control; the BOCOG operation team will move in; FF&E and other facilities will be loaded in.

The opening and closing of the Village: The Olympic Village will open on July 27, 2008 and close on August 28, 2008. The Paralympic Village will open on August 30 and close on September 20.

Application of the three concepts of the Olympic Games

The following green technologies have been applied: renewable energy, water reclamation, utilization of rain and flood, green building materials, energy-saving building, green indoor environment, ecological landscape, intelligent house, DTV, and green lighting, accessible facilities. The harmony between culture, architecture and environment has been achieved in the green residential area. The village, with its world leading technology, has showcased to the world the distinguishing characteristics of the high level Olympic Games.

The whole process of the construction illustrates the “three concepts”. For example, slag was used to pave the lanes at the construction sites; solar energy adopted for lighting; water sprayed to remove dust; water permeation bricks paved.

Utilization of renewable energy

Renewable energy utilized to save energy and cut emission During the Games-times, 7,890,000 kilowatt hours will be obtained from solar energy and reclaimed water for services.

After the Olympic Games, 67 million kilowatt hours will be obtained from solar energy and reclaimed water.

The reclaimed water heat pump air conditioning system

The system draws energy through heat exchange from the reclaimed water from the Qinghe Wastewater Treatment Plant and discharges the water to the rivers. During the process, the water quality will not change and water will not lessen while the energy in the reclaimed water can be utilized. The energy drawn from the reclaimed water can be enhanced by the heat pumps for heating and cooling. The system consumes electricity 40% less than the ordinary air conditioners. Thanks to the world leading wastewater utilization system, cooling towers or outdoor machines are not needed, no noise or smoke will be generated, and the heat island effect can be removed completely.

Integrated solar energy water heating system

The solar energy heating pipes are installed horizontally in the gardens on the roofs, constituting part of the pergola and thus integrated into the garden. 6,000 square metres solar energy water heating system can provide bathing hot water for more than 16,000 athletes. After the Olympic Games, it can provide hot water for nearly 2,000 households nearby.

All the details of the solar energy water heating system have been taken into consideration. They include heat collection, heat exchange, heat preservation, sterilization, heat source backup, waste heat utilization, automatic control, etc. The indirect cycle heat exchange is adopted in the system, featuring independent operation, consistent water temperature, easy maintenance and easy calculation. The solar energy water heating system can save 5 million kilowatt hours electric power per year. The scale and cutting edge technology have excelled those of the previous Olympic Games.

The solar collectors have been installed Street lamps with Solar/Wind Hybrid Power

Solar energy street lamps, garden lamps, lawn lamps, light pipes, green lighting such as LED lighting have been used to make the Olympic nights even more colorful.

Micro energy consumption building (Super Resident Center)

More than 20 cutting edge technologies, such as solar heat collection, solar water heating, solar dehumidification, cogeneration of heat and power by solar energy, windmill power generation, air conditioning by geo thermal heat pumps, vacuum windowpane, intellectual control, etc. have been applied in the micro energy consumption buildings. For 2,000 square metres of the micro energy consumption buildings, each square metre will consume 36 kilowatt hours annually, which is 1/3rd of the consumption of the existing energy saving buildings. 147,000 kilowatt hours of energy can be saved yearly.

Energy-saving buildings

Outer building enclosure heat preservation system

Thickened XPS extruded sheets have been used for walls and building surfaces, with heat transfer coefficient at 0.38w/ ㎡ .k. It can save energy while preserving heat. The heat insulation can make the buildings cool in summer and warm in winter.

Double-glazing LOW-E windowpanes

The double-glazing LOW-E glass with inert gases fill framed by aluminum has been used. The glass features thermal insulation and noise prevention. The K value (heat transfer coefficient) is close to 2.0. It can reduce the noise by 40db. The coating is of low radiant ratio. Such super thing low radiation coating can reflect most of the heat back to the room to prevent heat loss in winter. It can block the outdoor sun radiation in summer. The gas fill can cut the sound transmission to reduce noise while presenting good view.

Energy-saving Persian blinds

The heat transfer coefficient of the sealed insulating glass adopted for the Persian blinds is lower than ordinary ones. Therefore, it can save energy significantly. The blinds will be put into the cavity between the two layers of glass. The blinds can block solar radiation when closed to cut the energy consumption by the air conditioners. The blinds can absorb solar heat to keep the inside warm when opened. The magnetic system sealed within can control the movement of the slats. Thus, the solar radiation can be blocked while the view can be presented.

Environmental Protection

Biological sewage treatment technology used in landscape flowers house Biological sewage treatment technology is adopted in the Olympic Village to treat part of domestic waste water and also to provide water for landscape. Simulating the self-purification capacity of water, a water body biological balance system applying food chains of animals and plants is set up to treat the domestic water in a comprehensive way. In this way 200 tons of water can be provided to water the landscape.

Diagram of rain and flood water utilization

6000 m3of water can be collected and reused every year to water the green space and clean the road.

Application of environmental-friendly materials

In order to ensure a good indoor environment, construction materials(including cement, concrete, mixture, water reducing agent, wall materials, glass and glass wares, sanitary ceramics, doors and windows, water-proof materials) and decoration materials(artificial boards and products, coatings and paints, adhesives ) have been tested and undergone pre-control process during the construction. The environmental protection indicators of all these materials surpass the national standard E1, and reach E0 standard required by the Environmental Protection Guide of Olympic Projects.

High standard environmental-friendly paint

Quality Titanium dioxide white paint and wall paint with innovative environmental protection technology used in the Olympic Village are stain resistant and durable. The paint does not include heavy metals, content of the VOC(volatile organic compounds) and formaldehyde is close to zero.

Human oriented design ?Accessible design system Outdoors—Accessible ramps and blind sidewalks are set. The entrance and exit of apartments are level with the outside roads. Outdoor roads are higher than green space. Overhead wood plastic board is used to connect entrance and exit of a building with the outside roads, thus protecting the green space and facilitate people with walking difficulties. Public space—Accessible ramps and hand rails are installed at the main entrance of apartments and public facilities. Lifts tailor made for people with a disability are 900mm wide and accommodative for wheelchairs. Horizontal operating panels are provided in the lifts. Indoors—Accessible facilities are installed indoors. An accessible toilet is installed in each apartment on the ground, first and second floor, where sanitary wares and equipments up to the accessible design are used.

?High standard potable water system The deeply purified potable water (neutral Ph) tastes cool. Water goes through O3, activated carbon, ultrafiltration, nanofiltration, finished water storage tank, Catalyze Oxidation Sterilization, activated carbon, frequency conversion and pressure before reaching the users. Water is supplied around the clock thus avoiding the second time pollution in the pipelines. So high quality potable water is provided in the Olympic Village.

Excerpts from the BEIJING 2008 OLYMPIC GAMES - AN ENVIRONMENTAL REVIEW by UNEP: The venue features innovative technologies, such as a heat pump system, photovoltaic panels, beam-pipe illumination, solar collectors, water saving devices, and rainwater collection. The designers have succeeding in designing a people-oriented, healthy, comfortable and energy-saving environment in the Village.

(China.org.cn March 5, 2008)

Tools: Save | Print | E-mail | Most Read
Comment
Pet Name
Anonymous
China Archives
Related >>
Most Viewed >>
- A deal or a steal?
- White paper published on China's rule of law
- Nation vows full protection of IPR
- Presidium, agenda set for parliamentary session
- Illegal mining firms focus of campaign

Product Directory
China Search
Country Search
Hot Buys
亚洲精品久久久久久一区二区_99re热久久这里只有精品34_久久免费高清视频_一区二区三区不卡在线视频
欧美一区二区三区日韩视频| 欧美精品久久久久a| 亚洲激情网站免费观看| 亚洲一区二区三区精品视频| 99热免费精品| 亚洲精品一区二区三区99| 在线免费观看日韩欧美| 黑人巨大精品欧美一区二区小视频| 国产精品拍天天在线| 欧美午夜电影在线观看| 欧美日韩免费网站| 欧美日韩国产综合网| 欧美日韩国产小视频| 欧美日韩成人一区二区| 欧美啪啪一区| 欧美日韩精品免费观看| 欧美日韩国产高清视频| 欧美日韩精品综合| 欧美日韩中文字幕综合视频| 欧美日韩一级片在线观看| 欧美日韩国产在线播放网站| 欧美日韩国产999| 欧美日韩在线免费| 国产精品国产三级国产aⅴ无密码| 国产精品国产一区二区| 国产精品免费一区豆花| 国产精品色婷婷久久58| 国产日本精品| 狠狠色综合色综合网络| 一色屋精品视频在线观看网站| 狠狠色综合一区二区| 在线免费一区三区| 亚洲黄色影片| 亚洲作爱视频| 亚洲欧美一区二区视频| 欧美在线二区| 亚洲国产欧美国产综合一区| 亚洲精品你懂的| 亚洲视频在线观看一区| 午夜免费电影一区在线观看| 久久高清免费观看| 美脚丝袜一区二区三区在线观看 | 国产精品美女主播在线观看纯欲| 国产精品美女| 国内自拍一区| 91久久线看在观草草青青| 一区二区免费在线播放| 香蕉成人久久| 亚洲精品国精品久久99热一| 亚洲视频axxx| 久久久精品国产99久久精品芒果| 欧美xx视频| 国产精品久久久久久av下载红粉 | 亚洲国产一二三| 亚洲午夜免费福利视频| 久久精品亚洲热| 欧美人与禽猛交乱配| 国产精品成人va在线观看| 国语精品一区| 亚洲美女精品久久| 性欧美18~19sex高清播放| 亚洲精品美女在线| 午夜一级久久| 欧美精品成人在线| 国产亚洲成年网址在线观看| 亚洲精品孕妇| 久久精品盗摄| 午夜精品区一区二区三| 欧美大片国产精品| 国产伦精品一区二区三区视频孕妇| 亚洲第一区在线观看| 亚洲一区免费观看| 亚洲狼人综合| 久久黄色小说| 欧美啪啪一区| 激情另类综合| 亚洲一级片在线看| 亚洲人成在线影院| 久久精品一区四区| 国产精品黄视频| 亚洲黑丝一区二区| 欧美在线看片| 亚洲一区二区三区在线| 欧美成人综合| 国产欧美va欧美不卡在线| 日韩视频在线你懂得| 亚洲国产乱码最新视频| 久久精彩视频| 国产精品盗摄久久久| 亚洲精品1区2区| 亚洲福利视频在线| 久久av一区二区三区亚洲| 欧美日韩黄色一区二区| 在线观看视频欧美| 欧美一区二区精品久久911| 亚洲欧美另类中文字幕| 欧美日韩国产大片| 亚洲国产精品免费| 亚洲韩国一区二区三区| 久久精品国产在热久久| 国产精品女主播一区二区三区| 亚洲精品国产视频| 亚洲美女av黄| 欧美韩日一区二区| 在线观看av不卡| 久久精品一二三| 久久久91精品国产一区二区精品| 国产乱码精品一区二区三| 亚洲视频综合| 亚洲欧美日韩直播| 国产精品久久综合| 亚洲一区二区欧美| 亚洲欧美日本国产有色| 欧美视频精品在线观看| 亚洲免费观看在线观看| 99精品99| 欧美午夜a级限制福利片| 一本大道久久a久久精品综合| 夜夜嗨av一区二区三区四季av| 欧美精品日韩一区| 亚洲精品韩国| 一本色道久久综合亚洲精品婷婷| 欧美精品久久久久久久| 亚洲精品少妇30p| av成人动漫| 欧美日韩精品一区二区三区四区| 亚洲免费观看高清在线观看| 在线一区二区三区做爰视频网站| 欧美连裤袜在线视频| 亚洲精品资源| 亚洲一区在线免费| 国产精品久久久久毛片大屁完整版 | 国产欧美日韩91| 销魂美女一区二区三区视频在线| 欧美一级播放| 国产综合色在线| 91久久精品美女| 欧美人妖另类| 亚洲一区在线免费| 久久久噜噜噜久久中文字免| 在线观看一区| 夜夜精品视频| 国产麻豆成人精品| 亚洲国产精品久久久久婷婷老年| 欧美成人午夜77777| 亚洲精品国产精品乱码不99| 亚洲自拍偷拍福利| 国产伪娘ts一区 | 亚洲毛片在线看| 欧美三区免费完整视频在线观看| 亚洲视频专区在线| 久久久久久久91| 亚洲国产成人av| 亚洲在线视频一区| 国产一区二区日韩精品欧美精品| 91久久黄色| 国产精品美女在线| 久久国产精品亚洲77777| 欧美电影在线观看完整版| 9人人澡人人爽人人精品| 欧美一级视频精品观看| 精品av久久久久电影| 亚洲图片欧美一区| 国产亚洲午夜高清国产拍精品| 亚洲国产一区视频| 欧美日韩在线综合| 亚洲欧美日韩综合一区| 欧美成人精品激情在线观看 | 亚洲综合精品一区二区| 久久天天综合| 日韩一级黄色片| 久久久美女艺术照精彩视频福利播放| 亚洲高清精品中出| 午夜在线精品偷拍| 亚洲国产综合视频在线观看| 午夜久久一区| 亚洲国产网站| 欧美在线1区| 亚洲精品一区二区三区四区高清| 西西人体一区二区| 亚洲大片av| 性欧美xxxx大乳国产app| 亚洲国内欧美| 久久精品国产69国产精品亚洲| 亚洲精品乱码久久久久久| 久久国产日本精品| 一本色道久久综合狠狠躁篇的优点 | 国产精品不卡在线| 亚洲精品黄色| 国产亚洲精品久久久久婷婷瑜伽| 亚洲毛片在线观看.| 国产亚洲在线| 亚洲影院色在线观看免费| 亚洲电影在线免费观看| 欧美一区二区免费视频| 亚洲精品一区二区在线观看| 久久综合福利| 亚洲欧美一级二级三级| 欧美日韩亚洲一区二区三区| 91久久亚洲|